Construction overtime in Belgium: the KB 213 rules for 130 and 180 hours

Construction crew finishing a concrete floor on a Belgian building site on a summer evening

Status on 22 October 2026: the labour rules of royal decree no. 213 for construction are unchanged.

On the tax side, the law of 15 July 2026 made 180 tax-advantaged overtime hours permanent for all sectors from 1 January 2026.

Construction overtime in Belgium has its own scheme for joint committee 124: royal decree no. 213, often called KB 213.

If you register hours with a time tracking system for construction crews, KB 213 adds counters per worker that it has to get right.

It lets a crew work up to 1.5 extra hours a day, 130 hours a calendar year, or up to 180 in the summer-time period or a period of intense activity.

For each pay period, the worker chooses between payment with a 20% supplement and time off.

Below: one table with both regimes, then a summer season worked out for one crew.

KB 213 at a glance: the 130-hour and 180-hour regimes

The two regimes share most rules. What differs is how many hours you get and how you unlock them.

130-hour regime180-hour regime
WhoWorkers under joint committee 124 (construction)Workers under joint committee 124 (construction)
WhenWithin the calendar yearThe summer-time period, or a period of intense activity
Extra hours a dayUp to 1.5 (a 9.5-hour day)Up to 1.5 (a 9.5-hour day)
Extra hours a year130Up to 180
How you unlock itA majority of the union delegation agrees, or you inform the chair of joint committee 124A union majority agrees, or an accession protocol signed with at least one worker
Pay option20% supplement, Saturday always 50%20% supplement, Saturday always 50%
Time-off optionOne day off per 8 extra hours, within 12 monthsOne day off per 8 extra hours, within 12 months
No choice madeRest daysRest days
Tax benefitOn hours paid with the supplement, up to 180 a yearOn hours paid with the supplement, up to 180 a year
PaperworkWork rules updated, schedules announced 24 hours aheadWork rules updated, schedules announced 24 hours ahead

The labour rules in this table come from royal decree no. 213; the tax benefit comes from tax law.

Note: older pages say construction needs an electronic attendance registration on site to get the tax benefit on more than 130 hours. Since the law of 15 July 2026 made 180 hours permanent for every sector, that condition probably no longer matters; see the tax section below.

A summer season for one crew

Take a hypothetical crew of four on a housing project. All numbers here are round examples, not real pay data.

Their normal day is 8 hours. From May to September the site runs late to beat the autumn weather.

On 96 working days, each worker does 1.5 extra hours: a 9.5-hour day. That adds up to 144 extra hours each.

144 is more than 130, so the 130-hour regime is not enough.

The employer needs the 180-hour regime, which applies in the summer-time period.

That means a union majority, or an accession protocol with at least one worker, before the long days start.

Bricklayers on a scaffold working late in summer light to keep a site on schedule

What each worker can choose

Assume an hourly wage of EUR 20. Each pay period, before it ends, each worker makes a choice.

WorkerChoice for the seasonResult for 144 extra hours
1Payment144 x EUR 20 = EUR 2,880 base, + 20% = EUR 576, total EUR 3,456 gross
2Time off144 / 8 = 18 days off, to take within 12 months
3Payment in some pay periods, time off in others (half each)72 hours paid (EUR 1,728 gross) and 9 days off
4No choice madeRest days by default: 18 days

The 20% supplement and the rule of one day per 8 hours come from royal decree no. 213.

If any of these hours fall on a Saturday, the supplement for those hours is 50%.

All 144 hours fall within the first 180, so for worker 1 every paid hour qualifies for the tax benefit, and for worker 3 the 72 paid hours do.

Hours taken as time off carry no overtime pay, so there is no tax benefit on them.

What the site manager must track

  1. Hours per worker per day, so nobody goes above 9.5 hours under the scheme.
  2. The running total per worker, against 130 or 180 for the calendar year.
  3. The choice per pay period: payment, time off, or none.
  4. Days off owed and taken, within 12 months.
  5. The schedule, announced 24 hours ahead.

Tip: register the extra hours per worker on the site itself, the same day. A foreman’s notebook read out on Friday is where 144 turns into 139 or 151.

How to start the 180-hour regime before summer

The union step is what most sites forget until the long days have started. Plan it in spring.

Step 1: estimate the extra hours per worker

Count the days you expect to run long and multiply by 1.5. Above 130 hours, you need the 180-hour regime.

Step 2: get the agreement you need

For 130 hours: a majority of the union delegation, or you inform the chair of joint committee 124.

For 180 hours: a union majority, or an accession protocol with at least one worker.

Step 3: update the work rules

The work rules must reflect the scheme before you use it.

Step 4: announce schedules 24 hours ahead

Crews must know their longer days at least 24 hours in advance.

Step 5: record the choice and the days off

Note each worker’s choice before the end of every pay period. Plan the days off within 12 months.

How the general overtime rules fit in

Royal decree no. 213 is a sector scheme. Outside it, the general Belgian overtime rules apply.

Under those rules, overtime starts above 9 hours a day or 40 hours a week, or lower limits in a sector agreement or the work rules.

General overtime earns 50% extra on weekdays including Saturday, and 100% on Sundays and public holidays.

It also gives paid time off in lieu, normally within the quarter, extendable to 12 months.

That rest is paid at the normal wage when it is taken: it is the base pay for those hours, and the supplement comes on top when they are worked.

The absolute caps are 11 hours a day and 50 hours a week.

Sector agreements can change these rules, so always check your joint committee.

Do not mix it with voluntary overtime

Since 1 April 2026, every sector can also use up to 360 voluntary overtime hours a year, with the worker’s prior written agreement.

That is a separate regime. Only the first 240 voluntary hours are free of social security contributions and withholding tax.

And the 360 voluntary hours are not the 180 tax-advantaged overtime hours. Keep them in separate counters.

Construction overtime in Belgium: the tax side in 2026

The law of 15 July 2026 made 180 tax-advantaged overtime hours permanent for all sectors from 1 January 2026.

Some sectors get more: 280 hours for road and rail works, and 360 for horeca.

For construction, this suggests you no longer need a site registration system to reach 180 hours on the tax side.

That reading comes from one payroll source, not from the law’s own wording. Ask your social secretariat before you rely on it.

The labour rules of royal decree no. 213 did not change: the 130 and 180 hours, the union step and the worker’s choice stay as above.

Why registration still matters on site

Whatever the tax rule turns out to be, the scheme only works if every extra hour is counted per worker.

The 130 or 180 ceiling, the choice per pay period and the days off within 12 months all depend on it.

A common objection: "our foremen already have enough paperwork." Fair. If your crews register attendance for Check-in at Work, the same moment on site can capture start and end times.

Workforce management for construction crews turns those times into hours per worker that payroll can use.

For a real example, read how B&R Bouwgroep automated check-in on its construction sites.

Next step: set up time registration on your sites

Before next summer’s long days, make sure every crew registers hours on site.

Our guide to time registration in construction walks you through the options, from paper to an app.

Cool stuff

Service technician unloading tools from a van at a customer's house early in the morning

18/11/2026

Flexitime in Belgium: the rules, the registration and a worked week

Field technician loading tools into a van at a building site at the end of a long working day

13/11/2026

Overtime in Belgium: limits, pay and recovery rest, with a worked month